Survey for upcoming Route 132-138 milling
10/25/2013
The Capital Unit of the Mohawk Council of Kahnawà:ke would like to notify the Community that the company Topo 3D will be surveying Route 132/138 for upcoming milling works between the down ramps of the Mercier Bridge and Saint Francis Boulevard in Chateauguay. These works are necessary to ensure that proper surface drainage is maintained once the project is complete. The survey will take place on Monday, October 28th between 9:30am and 3:30pm, and should be completed the same day.
These works will be carried out within the roadway; however, traffic in both directions will be maintained at all times. Proper signalization will be placed to ensure everyone’s safety.
Your patience throughout this project is greatly appreciated and we apologize for the temporary inconvenience. If further information is required, please contact the Technical Services Office at (450) 635-1016.
|